Deans Community High School

« back to previous page

Livingston

Value:

Completion Year: Active Project

Deans Community High School is located in the town of Livingston and the new school, which opens in the summer of 2009, will provide modern teaching accommodation for approximately 1100 pupils.

The school design responds directly to the site context, the school and the community requirements. The design is centred on the main social space that extends into the courtyard, and the hub of the building. This separates large volume and noisy teaching environments from the standard classroom block which rises to 3 storeys in places.

The school has a large community use, both during and out of school hours. The public have access to the sports facilities that include games halls, a 25m swimming pool with spectator seating, 3 outdoor grass pitches and an all weather pitch. In addition, there are theatre facilities with an audience capacity of approximately 350 people, community clubs, offices and meeting spaces, and an under 5’s playgroup and crèche facility.

The new school is located closer to the main public highway than the exiting school, further enhancing its prominence as a community facility. The landscape design enhances the shape of the new school and introduces biodiversity into the landscape proposal which will enable the school in it outdoor curriculum.

During the construction phase Dawn Construction has employed numerous processes to reduce the impact of construction operations on the surrounding environment.

Deans Community High School 
BREEAM Rating and Score 56.31 (very good)
Basic Building Cost - £/m2 844.37
Services Cost - £/m2 367.85
External Works - £/m2 55.79
Gross Floor Area – m2 15454
Total Area of Site – hectares 6.3633
Area of Teaching Space – m2 4740.7
Area of Circulation – m2 2463
Area of Storage – m2 940.3
% Area of School Grounds to be used by Community 36
% Area of School Buildings to be used by Community 63
Predicted Electricity Consumption – kWh/m2 84
Predicted Fossil Fuel Consumption - kWh/m2 255
Predicted Renewable Energy Generation – kWh/m2 0
Predicted Water Use – m3/pupil/year 5.1
% Predicted Water Use to be Provided by Rainwater or Grey Water 0


Progress to 2nd Quarter 2008

Design  
Civil & External Work 80%
Structural  - Foundations 100%
                 - Frames 100%
Fabric 95%
Finishes 75%
Services 75%
 
Construction  
Enabling Work 100%
Foundations 100%
Structural Frame 100%
Fabric 95%
Fit-out  - 1st Stage 75%
             - 2nd Stage 20%
Services Installation 40%

Project Progress is compliant with Contract Programme